Engagement Period October 2015 – January 2016

The Challenge

Cloud21 were employed originally in an assurance role to provide board level confidence on the implementation of Lorenzo.

Following the identification of serious issues within the data migration workstream that were partially responsible for a delay to the programme, the Cloud21 data migration and informatics team were engaged to support a revised go live.

The Approach

The team initially reviewed and subsequently redeveloped significant elements of the logic used to define the source data and transform the data into IFFs for Lorenzo. The team were given limited time to resolve the most serious issues and limited opportunity to fully test the revised processes through ‘end to end’ loads. The team worked closely with the Trust and CSC to validate data within the IFFs against the CSC pre load validation tools (DVAS).

The team successfully delivered the Trust elements of the data migration over the weekend of 14th / 15th November 15.

The team delivered an ‘incomplete’ RTT position to within 318 records of the pre migration position. This was from a cohort of over 277,000 migrated pathways and an incomplete position of just over 29,000 pathways. Assurance of the RTT position was a critical determiner for the operational management to confirm the Trust decision to go live.

The team has continued to support the Trust to triage and in some cases resolve data migration issues and have also implemented the IDS to provide additional reporting metrics from the Lorenzo extracts and the Millennium source data.

How did our work deliver value to the Client?

Cloud21 were able to recover the position quickly, enabling the Trust to reach go live without further delays and with confidence in the migrated data. A seamless and reliable transition of service was delivered without significant risk or disruption to service.

The Trust had expected to undertake an extensive manual validation and data entry exercise post go live. The reconciliation activities completed by Cloud21 significantly reduced this timeline, enabling the Trust to quickly return to business as usual with confidence in the data they were working with.

Testimonial

“Thank you for getting us to this point of file submission. It’s quite outstanding the amount of work you’ve crammed in to these short weeks”

Simon Barron
Head of IT Systems Development
North Bristol NHS Trust

investors-in-people
tech-uk
microsoft-solutions-partner

Our use of cookies

We use necessary cookies to make our site work. We'd also like to set analytics cookies that help us make improvements by measuring how you use the site. These will be set only if you accept. For more detailed information about the cookies we use, see our Privacy Policy page.

Necessary cookies

Necessary cookies enable core functionality such as Google Captcha for our forms. You may disable these by changing your browser settings, but this may affect how the website functions.

Analytics cookies

We'd like to collect website analytics information using Google to help us improve the website. We collect this data by running Google Analytics JavaScript on your device, which collects data about how you have interacted with our site. The data is collected in a way that does not directly identify anyone. For more information please see our Privacy Policy page.


© Copyright 2026 Cloud21 Limited   |   All Rights Reserved

Registered in England & Wales   |   #06907257

If you require any content from the website in an alternative format, please email info@cloud21.net